4D seabed seismicCompletedNorth Sea
A 4D seabed seismic survey in the North Sea, acquired by Magseis Fairfield ASA for Aker BP ASA. Acquired from 30.03.2023 to 24.04.2023.
Planned start27.03.2023
Planned end30.04.2023
Started30.03.2023
Completed24.04.2023
Boat km planned685 km
Boat km done1 113 km
Net area planned, 3D and 4D205 km²
Net area acquired, 3D and 4D74 km²
Company doing the surveyMagseis Fairfield ASA
Acquired forAker BP ASA
Responsible companyAker BP ASA
Legal basisPetroleum regulations
SourceSeismic, 1 source
SensorsSeabed nodes
Offered to the marketNo
Survey area
The outline spans about 27 km east to west and 24 km north to south. The outline is the net area as reported, simplified to about 200 m.
Vessels
| Vessel | Role | Flag | IMO number |
|---|---|---|---|
| Normand Tonjer | Acquisition vessel | Norway | 9422108 |
| Oceanic Champion | Acquisition vessel | Norway | 9085211 |
| Shemarah II | Support vessel | United Kingdom | 9120889 |
Licence
The licences the survey is acquired under.
781, exploration licence
Weekly progress
From the company's latest weekly report. The register keeps the latest report only, not the weeks before it. Boat km is the distance sailed on line; CDP km is the length of the subsurface lines covered.
| Latest report covers | 17.04.2023 to 24.04.2023 |
| Boat km in the period | - |
| CDP km in the period | - |
| Boat km so far | 710 km |
| CDP km so far | - |
Notices
19 notices filed for the survey, newest first. The notices' own text is in Norwegian and is on FactPages.
| Date | Notice |
|---|---|
| 24.04.2023 | Status changed |
| 24.04.2023 | Survey completed |
| 17.04.2023 | Period report |
| 11.04.2023 | Period report |
| 30.03.2023 | Status changed |
| 30.03.2023 | Survey started |
| 14.02.2023 | Offshore Directorate on a change notice |
| 13.02.2023 | Change notice, for information |
| 13.02.2023 | Change notice, for information |
| 10.02.2023 | Directorate of Fisheries on a change notice |
| 07.02.2023 | Institute of Marine Research on a change notice |
| 06.02.2023 | Change notice for review |
| 19.01.2023 | Status changed |
| 19.01.2023 | Offshore Directorate on the notification |
| 16.01.2023 | Directorate of Fisheries on the notification |
| 27.12.2022 | Institute of Marine Research on the notification |
| 16.12.2022 | Status changed |
| 16.12.2022 | Change notice, for information |
| 16.12.2022 | Notification of the survey |