EQ21306
Site surveyCompletedNorwegian Sea
A site survey in the Norwegian Sea, acquired by Gardline Geosurvey Ltd for Equinor Energy AS. Acquired from 09.05.2021 to 31.05.2021.
Planned start20.04.2021
Planned end22.06.2021
Started09.05.2021
Completed31.05.2021
Boat km planned400 km
Boat km done224 km
Net area planned, 3D and 4D10 km²
Net area acquired, 3D and 4D4 km²
Company doing the surveyGardline Geosurvey Ltd
Acquired forEquinor Energy AS
Responsible companyEquinor Energy AS
Legal basisPetroleum regulations
SourceSeismic, 2 sources
SensorsStreamers, 1 200 m long
Offered to the marketNo
Survey area
The outline spans about 4,5 km east to west and 5,3 km north to south. The outline is the net area as reported, simplified to about 200 m.
Vessel
| Vessel | Role | Flag | IMO number |
|---|---|---|---|
| Ocean Resolution | Acquisition vessel | Panama | 9779446 |
Licences
The licences the survey is acquired under.
701, exploration licencePL 942
Weekly progress
From the company's latest weekly report. The register keeps the latest report only, not the weeks before it. Boat km is the distance sailed on line; CDP km is the length of the subsurface lines covered.
| Latest report covers | 24.05.2021 to 30.05.2021 |
| Boat km in the period | 224 km |
| CDP km in the period | - |
| Boat km so far | 276 km |
| CDP km so far | - |
| Next period planned | 31.05.2021 to -, - |
Notices
13 notices filed for the survey, newest first. The notices' own text is in Norwegian and is on FactPages.
| Date | Notice |
|---|---|
| 31.05.2021 | Survey completed |
| 30.05.2021 | Status changed |
| 25.05.2021 | Period report |
| 18.05.2021 | Period report |
| 10.05.2021 | Period report |
| 09.05.2021 | Status changed |
| 09.05.2021 | Survey started |
| 19.04.2021 | Status changed |
| 19.04.2021 | Offshore Directorate on the notification |
| 15.04.2021 | Institute of Marine Research on the notification |
| 25.03.2021 | Directorate of Fisheries on the notification |
| 15.03.2021 | Status changed |
| 15.03.2021 | Notification of the survey |