NEP20301
Site surveyCompletedNorwegian Sea
A site survey in the Norwegian Sea, acquired by Fugro Survey AS for Neptune Energy Norge AS. Acquired from 10.06.2020 to 16.06.2020.
Planned start25.05.2020
Planned end01.07.2020
Started10.06.2020
Completed16.06.2020
Boat km planned182 km
Boat km done182 km
Net area planned, 3D and 4D16 km²
Net area acquired, 3D and 4D16 km²
Company doing the surveyFugro Survey AS
Acquired forNeptune Energy Norge AS
Responsible companyNeptune Energy Norge AS
Legal basisPetroleum regulations
SourceSeismic
SensorsStreamers
Offered to the marketNo
Survey area
The outline spans about 5,4 km east to west and 6,7 km north to south. The outline is the net area as reported, simplified to about 200 m.
Vessel
| Vessel | Role | Flag | IMO number |
|---|---|---|---|
| Fugro Meridian | Acquisition vessel | Bahamas | 8101331 |
Licence
The licences the survey is acquired under.
Weekly progress
From the company's latest weekly report. The register keeps the latest report only, not the weeks before it. Boat km is the distance sailed on line; CDP km is the length of the subsurface lines covered.
| Boat km in the period | 182 km |
| CDP km in the period | - |
| Boat km so far | 358 km |
| CDP km so far | - |
Notices
10 notices filed for the survey, newest first. The notices' own text is in Norwegian and is on FactPages.
| Date | Notice |
|---|---|
| 16.06.2020 | Status changed |
| 16.06.2020 | Weekly report |
| 16.06.2020 | Completion notice |
| 11.06.2020 | Start notice |
| 10.06.2020 | Status changed |
| 22.04.2020 | Status changed |
| 22.04.2020 | Consultation comment, Institute of Marine Research |
| 22.04.2020 | Offshore Directorate letter to the companies |
| 21.04.2020 | Consultation comment, Directorate of Fisheries |
| 16.04.2020 | Status changed |