PGS23002
3D seismicCompletedNorwegian Sea
A 3D seismic survey in the Norwegian Sea for Multiklient Invest AS. Acquired from 26.06.2023 to 20.09.2023.
Planned start26.06.2023
Planned end30.09.2023
Started26.06.2023
Completed20.09.2023
Boat km planned-
Boat km done445 328 km
Net area planned, 3D and 4D8 000 km²
Net area acquired, 3D and 4D4 955 km²
Company doing the surveyMultiklient Invest AS
Acquired forMultiklient Invest AS
Responsible companyMultiklient Invest AS
Legal basisPetroleum regulations
SourceSeismic, 3 sources
SensorsStreamers, 7 500 m long
Offered to the marketYes
Survey area
The outline spans about 195 km east to west and 174 km north to south. The outline is the net area as reported, simplified to about 200 m.
Vessels
| Vessel | Role | Flag | IMO number |
|---|---|---|---|
| Ramform Hyperion | Acquisition vessel | Bahamas | 9676890 |
| Ramform Victory | Acquisition vessel | Norway | 9178630 |
Licence
The licences the survey is acquired under.
843, exploration licence
Weekly progress
From the company's latest weekly report. The register keeps the latest report only, not the weeks before it. Boat km is the distance sailed on line; CDP km is the length of the subsurface lines covered.
| Latest report covers | 11.09.2023 to 20.09.2023 |
| Boat km in the period | - |
| CDP km in the period | - |
| Boat km so far | 11 901 km |
| CDP km so far | - |
Notices
31 notices filed for the survey, newest first. The notices' own text is in Norwegian and is on FactPages.
| Date | Notice |
|---|---|
| 20.09.2023 | Status changed |
| 20.09.2023 | Survey completed |
| 11.09.2023 | Status changed |
| 11.09.2023 | Period report |
| 11.09.2023 | Survey paused |
| 06.09.2023 | Period report |
| 29.08.2023 | Period report |
| 21.08.2023 | Period report |
| 14.08.2023 | Period report |
| 07.08.2023 | Period report |
| 31.07.2023 | Period report |
| 26.07.2023 | Period report |
| 17.07.2023 | Period report |
| 11.07.2023 | Period report |
| 11.07.2023 | Change notice, for information |
| 04.07.2023 | Period report |
| 04.07.2023 | Change notice, for information |
| 04.07.2023 | Change notice, for information |
| 26.06.2023 | Status changed |
| 26.06.2023 | Survey started |
| 21.06.2023 | Change notice, for information |
| 21.06.2023 | Change notice, for information |
| 05.06.2023 | Change notice, for information |
| 05.06.2023 | Change notice, for information |
| 08.05.2023 | Status changed |
| 08.05.2023 | Offshore Directorate on the notification |
| 04.05.2023 | Institute of Marine Research on the notification |
| 03.05.2023 | Directorate of Fisheries on the notification |
| 03.05.2023 | Change notice, for information |
| 28.04.2023 | Status changed |
| 28.04.2023 | Notification of the survey |