TEPN-12-5
Site surveyCompletedNorth Sea
A site survey in the North Sea for Total E&P Norge AS. Acquired from 29.11.2012 to 25.03.2013.
Planned start20.11.2012
Planned end04.03.2013
Started29.11.2012
Completed25.03.2013
Boat km planned3 000 km
Boat km done3 000 km
Company doing the surveyTotal E&P Norge AS
Acquired forTotal E&P Norge AS
Responsible companyTotal E&P Norge AS
Legal basisPetroleum regulations
SourceSeismic
SensorsStreamers
Offered to the marketNo
Survey area
The outline spans about 21 km east to west and 31 km north to south. The outline is the net area as reported, simplified to about 200 m.
Weekly progress
From the company's latest weekly report. The register keeps the latest report only, not the weeks before it. Boat km is the distance sailed on line; CDP km is the length of the subsurface lines covered.
| Boat km in the period | 3 000 km |
| CDP km in the period | - |
| Boat km so far | 3 706 km |
| CDP km so far | - |
Notices
18 notices filed for the survey, newest first. The notices' own text is in Norwegian and is on FactPages.
| Date | Notice |
|---|---|
| 06.03.2013 | Status changed |
| 06.03.2013 | Completion notice |
| 20.02.2013 | Change notice |
| 25.01.2013 | Change notice |
| 10.01.2013 | Weekly report |
| 02.01.2013 | Weekly report |
| 17.12.2012 | Status changed |
| 17.12.2012 | Start notice |
| 17.12.2012 | Weekly report |
| 27.11.2012 | Offshore Directorate letter to the companies |
| 26.11.2012 | Consultation comment, Institute of Marine Research |
| 20.11.2012 | Offshore Directorate letter to the companies |
| 20.11.2012 | Status changed |
| 19.11.2012 | Consultation comment, Institute of Marine Research |
| 12.11.2012 | Consultation comment, Directorate of Fisheries |
| 09.11.2012 | Change notice |
| 09.11.2012 | Change notice |
| 24.10.2012 | Status changed |