WellplannerNorwegian shelf well data

Fields / Gyda / 2/1-A-28

2/1-A-28

Development, productionPluggedOil

Drilled by BP Norway Limited U.A. with Gyda in Gyda, 30.10.1995 to 31.12.1995 (62 days), to 4 968,0 m.

Water depth65,5 m
Total depth4 968,0 m MD
Vertical depth4 140,0 m TVD
Bottom-hole temperature-
Max inclination-
Rotary table56,0 m
Formation at total depth-
RigGyda
Spud30.10.1995
Completed31.12.1995
OperatorBP Norway Limited U.A.
Position56,9048 N, 3,0850 E

Formations

No formation tops are reported for this wellbore. The register publishes tops for released exploration wells.

Temperature

Reported at total depth-
Gyda gradient37,0 °C/km
Estimated at total depth from the gradient153 °C

The gradient is the median of 6 released wells in Gyda with a reported bottom-hole temperature, counted from 4 °C at the sea floor.

Offset wells

The nearest wellbores within 15 km, straight-line distance at the surface.

WellborekmTotal depth, mBHTMud max, g/cm³Year
2/1-A-28 A same well0,04 850,0--2008
2/1-A-320,05 897,0--1994
2/1-A-32 A0,06 134,0--2006
2/1-A-32 B0,04 438,0--2008
2/1-A-32 C0,06 939,0--2012
2/1-A-32 D0,08 408,0--2013
2/1-A-240,05 423,0--1992
2/1-A-24 A0,05 115,0--1992

Casing and formation tests

No casing programme is reported for this wellbore.