WellplannerNorwegian shelf well data

Fields / Gyda / 2/1-A-24 A

2/1-A-24 A

Development, productionPluggedOil

Drilled by BP Norway Limited U.A. with Gyda in Gyda, 25.12.1992 to 30.01.1993 (36 days), to 5 115,0 m.

Water depth66,0 m
Total depth5 115,0 m MD
Vertical depth4 342,0 m TVD
Bottom-hole temperature-
Max inclination-
Rotary table56,0 m
Formation at total depth-
RigGyda
Spud25.12.1992
Completed30.01.1993
OperatorBP Norway Limited U.A.
Position56,9048 N, 3,0850 E

Formations

No formation tops are reported for this wellbore. The register publishes tops for released exploration wells.

Temperature

Reported at total depth-
Gyda gradient37,0 °C/km
Estimated at total depth from the gradient160 °C

The gradient is the median of 6 released wells in Gyda with a reported bottom-hole temperature, counted from 4 °C at the sea floor.

Offset wells

The nearest wellbores within 15 km, straight-line distance at the surface.

WellborekmTotal depth, mBHTMud max, g/cm³Year
2/1-A-24 same well0,05 423,0--1992
2/1-A-24 B same well0,05 200,0--1995
2/1-A-230,04 975,0--1991
2/1-A-200,04 387,0--1993
2/1-A-280,04 968,0--1995
2/1-A-28 A0,04 850,0--2008
2/1-A-190,04 580,0--1992
2/1-A-19 A0,04 630,0--2010

Casing and formation tests

No casing programme is reported for this wellbore.

Show on the mapOpen on FactPages ↗