Fields / 25/8-U-5
25/8-U-5
Other, unknownPlugged and abandoned
Drilled by Esso Exploration and Production Norway A/S with Bucentaur, 25.08.1996 to 25.08.1996 (0 days), to 172,0 m.
Water depth126,0 m
Total depth172,0 m MD
Vertical depth-
Bottom-hole temperature-
Max inclination-
Rotary table2,9 m
Formation at total depth-
RigBucentaur
Spud25.08.1996
Completed25.08.1996
OperatorEsso Exploration and Production Norway A/S
Position59,4536 N, 2,4126 E
Formations
No formation tops are reported for this wellbore. The register publishes tops for released exploration wells.
Temperature
| Reported at total depth | - |
The wellbore is not in a field, so no field gradient applies.
Offset wells
The nearest wellbores within 15 km, straight-line distance at the surface.
Casing and formation tests
No casing programme is reported for this wellbore.