WellplannerNorwegian shelf well data

Fields / Oseberg / 30/9-B-14

30/9-B-14

Development, observationPlugged

Drilled by Norsk Hydro Produksjon AS with Oseberg B in Oseberg, 26.04.1996 to 18.05.1996 (22 days), to 4 223,0 m.

Water depth109,0 m
Total depth4 223,0 m MD
Vertical depth2 713,5 m TVD
Bottom-hole temperature-
Max inclination-
Rotary table58,0 m
Formation at total depth-
RigOseberg B
Spud26.04.1996
Completed18.05.1996
OperatorNorsk Hydro Produksjon AS
Position60,4934 N, 2,8285 E

Formations

No formation tops are reported for this wellbore. The register publishes tops for released exploration wells.

Temperature

Reported at total depth-
Oseberg gradient38,1 °C/km
Estimated at total depth from the gradient101 °C

The gradient is the median of 29 released wells in Oseberg with a reported bottom-hole temperature, counted from 4 °C at the sea floor.

Offset wells

The nearest wellbores within 15 km, straight-line distance at the surface.

WellborekmTotal depth, mBHTMud max, g/cm³Year
30/9-B-14 A same well0,05 796,0--1996
30/9-B-14 B same well0,08 912,0--2002
30/9-B-14 C same well0,06 632,0--2017
30/9-B-14 D same well0,06 023,0--2017
30/9-B-14 E same well0,07 693,0--2018
30/9-B-130,03 492,0--1989
30/9-B-13 A0,07 666,0--1998
30/9-B-80,03 655,0--1991

Casing and formation tests

No casing programme is reported for this wellbore.

Show on the mapOpen on FactPages ↗