Site surveyCompletedNorth Sea

A site survey in the North Sea, acquired by Fugro Geotechnics AS for Centrica Resources (Norge) AS. Acquired from 27.05.2017 to 29.05.2017.

Planned start18.05.2017
Planned end05.06.2017
Started27.05.2017
Completed29.05.2017
Boat km planned10 km
Boat km done10 km
Company doing the surveyFugro Geotechnics AS
Acquired forCentrica Resources (Norge) AS
Responsible companyCentrica Resources (Norge) AS
Legal basisPetroleum regulations
Offered to the marketNo

Survey area

57,08° N57,05° N3,03 to 3,10° E

The outline spans about 4,0 km east to west and 4,0 km north to south. The outline is the net area as reported, simplified to about 200 m.

Vessels

No vessel is named for this survey in the register.

Licence

The licences the survey is acquired under.

PL 405

Weekly progress

From the company's latest weekly report. The register keeps the latest report only, not the weeks before it. Boat km is the distance sailed on line; CDP km is the length of the subsurface lines covered.

100 % of the planned boat km
Boat km in the period10 km
CDP km in the period-
Boat km so far10 km
CDP km so far-

Notices

11 notices filed for the survey, newest first. The notices' own text is in Norwegian and is on FactPages.

DateNotice
29.05.2017Status changed
29.05.2017Status changed
29.05.2017Start notice
29.05.2017Completion notice
19.05.2017Consultation comment, Directorate of Fisheries
12.05.2017Change notice
03.04.2017Status changed
02.04.2017Offshore Directorate letter to the companies
31.03.2017Consultation comment, Institute of Marine Research
28.03.2017Consultation comment, Directorate of Fisheries
15.03.2017Status changed