EQ25205
4D seabed seismicCompletedNorth Sea
A 4D seabed seismic survey in the North Sea, acquired by TGS ASA for Equinor Energy AS. Acquired from 26.08.2025 to 01.10.2025.
Planned start25.08.2025
Planned end07.10.2025
Started26.08.2025
Completed01.10.2025
Boat km planned2 572 km
Boat km done2 613 km
Net area planned, 3D and 4D385 km²
Net area acquired, 3D and 4D386 km²
Company doing the surveyTGS ASA
Acquired forEquinor Energy AS
Responsible companyEquinor Energy AS
Legal basisPetroleum regulations
SourceSeismic, 3 sources
SensorsSeabed nodes
Offered to the marketNo
Survey area
The outline spans about 33 km east to west and 34 km north to south. The outline is the net area as reported, simplified to about 200 m.
Weekly progress
From the company's latest weekly report. The register keeps the latest report only, not the weeks before it. Boat km is the distance sailed on line; CDP km is the length of the subsurface lines covered.
| Latest report covers | 29.09.2025 to 01.10.2025 |
| Boat km in the period | 172 km |
| CDP km in the period | - |
| Boat km so far | 2 612 km |
| CDP km so far | - |
Notices
21 notices filed for the survey, newest first. The notices' own text is in Norwegian and is on FactPages.
| Date | Notice |
|---|---|
| 01.10.2025 | Status changed |
| 01.10.2025 | Survey completed |
| 30.09.2025 | Directorate of Fisheries on a change notice |
| 29.09.2025 | Period report |
| 29.09.2025 | Change notice for review |
| 22.09.2025 | Period report |
| 15.09.2025 | Period report |
| 08.09.2025 | Period report |
| 01.09.2025 | Period report |
| 28.08.2025 | Offshore Directorate on a change notice |
| 26.08.2025 | Status changed |
| 26.08.2025 | Survey started |
| 25.08.2025 | Institute of Marine Research on a change notice |
| 19.08.2025 | Directorate of Fisheries on a change notice |
| 15.08.2025 | Change notice for review |
| 16.06.2025 | Change notice, for information |
| 22.04.2025 | Status changed |
| 22.04.2025 | Offshore Directorate on the notification |
| 16.04.2025 | Directorate of Fisheries on the notification |
| 14.03.2025 | Institute of Marine Research on the notification |
| 10.03.2025 | Status changed |