WP23300
Site surveyCompletedNorth Sea
A site survey in the North Sea, acquired by Fugro Norway AS for Wellesley Petroleum AS. Acquired from 18.10.2023 to 29.10.2023.
Planned start15.10.2023
Planned end15.11.2023
Started18.10.2023
Completed29.10.2023
Boat km planned200 km
Boat km done220 km
Net area planned, 3D and 4D36 km²
Net area acquired, 3D and 4D-
Company doing the surveyFugro Norway AS
Acquired forWellesley Petroleum AS
Responsible companyWellesley Petroleum AS
Legal basisPetroleum regulations
SourceSeismic, 1 source
SensorsStreamers, 1 200 m long
Offered to the marketNo
Survey area
The outline spans about 7,8 km east to west and 7,8 km north to south. The outline is the net area as reported, simplified to about 200 m.
Vessel
| Vessel | Role | Flag | IMO number |
|---|---|---|---|
| Fugro Meridian | Acquisition vessel | Bahamas | 8101331 |
Licence
The licences the survey is acquired under.
Weekly progress
From the company's latest weekly report. The register keeps the latest report only, not the weeks before it. Boat km is the distance sailed on line; CDP km is the length of the subsurface lines covered.
| Latest report covers | 26.10.2023 to 29.10.2023 |
| Boat km in the period | - |
| CDP km in the period | - |
| Boat km so far | 180 km |
| CDP km so far | - |
Notices
16 notices filed for the survey, newest first. The notices' own text is in Norwegian and is on FactPages.
| Date | Notice |
|---|---|
| 25.02.2025 | Directorate of Fisheries on a change notice |
| 29.10.2023 | Status changed |
| 29.10.2023 | Survey completed |
| 26.10.2023 | Period report |
| 18.10.2023 | Status changed |
| 18.10.2023 | Survey started |
| 18.10.2023 | Change notice, for information |
| 18.10.2023 | Change notice, for information |
| 03.10.2023 | Institute of Marine Research on a change notice |
| 28.09.2023 | Change notice for review |
| 31.08.2023 | Status changed |
| 31.08.2023 | Offshore Directorate on the notification |
| 30.08.2023 | Institute of Marine Research on the notification |
| 30.08.2023 | Directorate of Fisheries on the notification |
| 24.08.2023 | Status changed |
| 24.08.2023 | Notification of the survey |