Other, soil drillingPlugged and abandoned

Drilled by Lundin Norway AS with Bucentaur, 29.01.2008 to 29.01.2008 (0 days), to 151,6 m.

Water depth119,5 m
Total depth151,6 m MD
Vertical depth-
Bottom-hole temperature-
Max inclination-
Rotary table3,0 m
Formation at total depth-
RigBucentaur
Spud29.01.2008
Completed29.01.2008
OperatorLundin Norway AS
Position59,7446 N, 2,3942 E

Formations

No formation tops are reported for this wellbore. The register publishes tops for released exploration wells.

Temperature

Reported at total depth-

The wellbore is not in a field, so no field gradient applies.

Offset wells

The nearest wellbores within 15 km, straight-line distance at the surface.

WellborekmTotal depth, mBHTMud max, g/cm³Year
25/5-U-70,1164,3--2008
25/5-U-90,1151,3--2008
25/5-60,72 446,0-1,392009
25/2-16 S1,24 013,0121 °C1,502001
25/2-U-155,01 356,0--2023
25/2-E-6 H5,0---2026
25/2-E-4 H5,0---2026
25/4-6 S5,84 170,0143 °C1,751991

Casing and formation tests

No casing programme is reported for this wellbore.